How helium leak testing is billed
| Service | How it is usually billed | Illustrative planning range |
|---|---|---|
| Field sniffer scan of welds and flanges | Per crew day, two person team with detector | $1,400 to $2,600 per day |
| Vacuum (spray) test of a chamber or vessel | Per day plus pump and fixture setup | $1,800 to $3,200 per day |
| Heat exchanger tube bundle test | Per bundle, often a one or two day job | $4,000 to $9,000 per bundle |
| Shop hood or chamber test of a sealed part | Per part, falls with batch size | $60 to $400 per part |
| Reference leak calibration and certificate | Per job | $150 to $450 |
| Report with leak rates and locations | Per report or included | $200 to $600 |
Mobilization, travel, helium and a minimum charge apply on field jobs. Production shops quote sealed parts by the piece once a fixture exists, and the fixture is a one time line of its own. Helium is billed at cost in most quotes, and a large vessel can use more than a small job suggests.
Worked example, one leaking shell and tube exchanger
Assume a stainless shell and tube exchanger with 220 tubes that has lost vacuum on the shell side. The owner needs the leaking tubes found, plugged and the unit retested. These inputs are assumed for the example.
| Line | Quantity | Planning figure |
|---|---|---|
| Mobilization and travel within the region | 1 | $600 |
| Crew day, setup, helium supply and calibration | 1 day | $2,200 |
| Tube end probing, 220 tubes, leaking tubes marked | 1 day | $2,200 |
| Retest after plugging | half day | $1,100 |
| Helium and consumables | 1 | $350 |
| Report with tube map and leak rates | 1 | $400 |
| Total | about $6,850 |
That is roughly $31 per tube, and a second repair and retest cycle adds about $1,100 to $2,200. A quote that does not say how a second retest is priced is the one that surprises you at invoice time. If the exchanger also needs a wall loss survey while the heads are off, see heat exchanger inspection services and eddy current testing for combining scopes.
What moves the price up or down
- Required leak rate. Tighter limits need a mass spectrometer with a clean vacuum setup and longer pump down. State the number and its unit in the request.
- Preparation. Draining, drying, blanking flanges and installing test connections are often more work than the test itself.
- Part size and joint count. More tubes, flanges and welds mean more probing time.
- Retests. Every repair and retest cycle adds hours, and a clear quote prices the first retest and each one after.
- Site and mobilization. A distant plant adds travel, and a daily minimum applies to short jobs.
- Witness and reporting. A customer witnessed test or traceable calibration adds a line.
Where the leak rate and procedure come from
The method follows ASME Boiler and Pressure Vessel Code Section V, Article 10 on leak testing, which covers tracer gas and mass spectrometer testing. The accepted leak rate is not set by the method. It comes from your drawing, specification or customer, so write it in the request. The code text is published by ASME. The service page for the method itself is helium leak testing services.
Who should read this, and who should not
This guide fits plant engineers with a leaking exchanger or vacuum system, equipment makers who must prove a leak rate before delivery, and maintenance managers budgeting a recommissioning. It does not help if you only need a code pressure proof, where a hydrostatic testing quote is cheaper and is what the code asks for. If the leak is in a tank floor, vacuum box testing services cost less than helium.
How to get comparable quotes
- Give the part type, size, material and the number of tubes, joints or welds.
- State the required leak rate, its unit and the document that sets it.
- Say whether the part can be pressurized, evacuated or both, and the maximum pressure.
- Say who drains, dries and blanks the system.
- Ask each company to price mobilization, setup, test time, retest and report as separate lines.
You can send one request to several companies through the NDT companies directory, and the NDT inspection cost guide shows how other methods compare.
How much does helium leak testing cost?
Field helium leak testing runs about $1,400 to $2,600 per crew day, sealed parts in a shop $60 to $400 each, and a tube bundle search often $4,000 to $9,000. Preparation and retests change the total more than detector time.
How long does helium leak testing take?
A sniffer scan of a few welds is a half day. A heat exchanger tube bundle is usually one to two days, and a large vacuum chamber can take two days including pump down. Retest after repair adds half a day or more.
Is helium leak testing worth the cost compared with a pressure test?
It is worth it when a leak rate is specified or a leak cannot be found with soap solution. A pressure or hydrostatic test proves strength and gross tightness only, so many parts get both tests.
Who performs helium leak testing?
Leak testing companies, NDT firms and some equipment service shops perform it with a mass spectrometer detector. Ask for the technician's qualification and the detector's last calibration. One request through the NDT companies page lets you compare several.