Inline inspection pipeline cost per mile and per run

An inline inspection (ILI) program on a mid size US pipeline is usually priced as a bundle: cleaning runs, a gauging run, the metal loss run with analysis, and verification digs. The run itself is often the smaller part. On an illustrative 18 mile, 12 inch liquid line the total lands around $250,000 to $400,000, and the digs alone can be half of it. Per mile cost falls as length rises, because mobilization and report minimums spread over more pipe.

Inline inspection pipeline cost per mile and per run

Inline inspection cost by line item

These are planning ranges for a 8 to 24 inch US line, built from the way providers typically structure quotes. Real quotes vary with diameter, wall, product, tool availability and schedule, so use the table to check a quote for gaps, not to replace one.

Line itemPlanning rangeWhat moves it
Cleaning pig runs $3,000 to $12,000 per run Product, debris, number of runs, pig type
Gauging or caliper run $8,000 to $25,000 Diameter, length, restrictions found
MFL metal loss run with analysis $40,000 to $150,000 per run Diameter, length, tool availability, data volume
Ultrasonic inline inspection run 1.5 to 2.5 times a comparable MFL run Liquid medium, wall thickness, crack detection option
Temporary launcher and receiver, or trap modifications $5,000 to $60,000 Whether permanent traps exist, hot work, tie ins
Field support crew and tool tracking $2,000 to $5,000 per day Run duration, remote location
Report and integrity assessment Often in the run price, or $10,000 to $40,000 as an extra Preliminary list, ASME B31G assessment, dig list
Verification dig $15,000 to $60,000 each Depth, soil, road or river crossing, coating repair

Short lines pay more per mile because the mobilization, tool and report minimums do not shrink with length. Operators with several lines in one region often bundle runs into a single mobilization to bring that down.

Worked budget for an 18 mile, 12 inch liquid line

Take a refined products line, 12 inch, 0.25 inch wall, 18 miles, with permanent launcher and receiver traps and a 1998 coating. The operator wants a metal loss baseline and a dig list.

  • Two cleaning runs at $6,000, about $12,000.
  • One gauging run, about $14,000, to prove the tool will pass.
  • One MFL run with analysis, about $85,000.
  • Field support crew for the three runs across 4 days at $3,500, about $14,000.
  • Preliminary and final report with an ASME B31G assessment, about $20,000.
  • Six verification digs at an average $30,000, about $180,000, including coating repair.
  • Operator project management and product handling, about $15,000.

That is roughly $340,000, or about $19,000 per mile. Change one input and the number moves. If the gauging run finds a restriction, add a second gauging pass and the cost of removing it. If no permanent traps exist, add up to $60,000 for temporary ones. If the analysis flags only two digs, the total drops by $120,000 and the run itself becomes the larger line. For a 2 mile line the same fixed items would give a per mile cost several times higher.

What moves an inline inspection quote

Line condition is the first driver. A line that has never been pigged or that carries paraffin, scale or sludge needs more cleaning runs, and an MFL tool run on a dirty line gives poor data and a second run. Ask the provider what cleaning criteria must be met before the tool goes in.

Piggability is the second. Plug valves, reduced bore valves, mitered bends, tight radius elbows and diameter changes can stop a tool, which is why the gauging run comes first. When the answer is no, the program moves to modifications or to the robotic and external options in our pipeline metal loss inspection services page.

Tool choice is third. MFL is the usual baseline choice and covers gas or liquid. Ultrasonic inline inspection costs more and needs a liquid medium, but it gives direct wall thickness and suits thick wall or crack questions. The pipeline inspection page explains which threats each tool class sees.

The fourth driver is the dig program. Operators sometimes compare quotes only on the run price and discover later that tool accuracy decides how many digs they have to open. A tool with tighter sizing tolerance at your wall thickness can save more than its price difference.

Where the requirement comes from

Regulated operators run ILI to satisfy integrity management rules. For gas transmission the rules sit in 49 CFR Part 192 Subpart O, and for hazardous liquids in 49 CFR 195.452. API 1163 covers qualification of the inline inspection systems and the analysts who report on them. Ask any bidder to state which tool specification applies to your diameter and wall, and what the stated probability of detection and sizing tolerance are.

What to send for comparable inline inspection quotes

  • Diameter, nominal wall, grade, length and installation year.
  • Product, pressure range, flow rate and temperature.
  • Trap type and dimensions, valve types and known bends or reductions.
  • Last ILI date, vendor and report, if any.
  • Required threats: metal loss only, or also dents, cracks and mechanical damage.
  • Cleaning scope and who supplies the pigs.
  • Dig program responsibility, report format and assessment method.
  • Run window, product constraints and shutdown limits.

How much does an inline pipeline inspection cost per mile?

A rough range is $5,000 to $25,000 per mile for a program that includes cleaning, gauging, the run and the report, and well over that for short lines because of fixed minimums. Verification digs come on top. Our worked 18 mile example lands near $19,000 per mile with digs.

How much does an MFL inspection cost?

The MFL run with analysis typically costs $40,000 to $150,000 for an 8 to 24 inch line, depending on diameter, length and tool availability. Add cleaning, gauging, temporary traps and field support. A short line with a single run often costs more per mile than a long one.

Is ultrasonic inline inspection more expensive than MFL?

Usually yes, about 1.5 to 2.5 times a comparable MFL run. Ultrasonic tools need a liquid coupling medium, which means a batch for gas lines, and they generate more data. They are chosen when direct wall thickness, thick wall or crack detection matters more than price per mile.

Who pays for the digs after an inline inspection?

The pipeline owner pays for verification digs and repairs, since they are part of the operator's integrity program. Some providers include a few field verifications in the run price, but excavation, coating repair and backfill are normally separate. Put the dig responsibility in the quote request.

How often is inline inspection required?

For gas transmission segments in high consequence areas, 49 CFR 192 Subpart O sets reassessment at intervals of up to seven years for most segments, shorter when anomalies need action. Hazardous liquid operators follow 49 CFR 195.452. Many operators schedule more often when corrosion growth is high.